Project

Liberty Hill Road

MGP Remediation

  • Liberty Utilities
  • Commercial
  • Gilford, NH

Project Overview

What is now a beautiful residential neighborhood in Gilford, NH was once home to the Messer Street Manufactured Gas Plant circa 1952. The plant was used to remove liquid coal tar from equipment, which was then disposed of in a gravel pit along Liberty Hill Road. The pit was backfilled and in the 70’s the surrounding area was developed into a residential neighborhood. It wasn’t until site investigations in 2004 by Liberty Utilities, who acquired the site, that the contamination of the area came to light. Following nearly 10 years of thorough site investigations and multiple public forums, Charter was awarded the contract to remediate the 4.5 acre MGP impacted site. Over the course of two construction seasons, over 93,000 cy of MGP coal impacted materials was removed from the site, 40,000+ of which received thermal treatment. Charter also performed demolition of existing structures, such as remnant foundations, tanks, and driveways, and treated contaminated stormwater and groundwater on site before discharge. Once the remediation and final restoration was complete, the site was reopened for selective recreational use.

Commitment to Safety

Given the site’s proximity to a residential community, the project team took extra precautions to ensure not only the safety of workers, but also those living in the surrounding areas. The site was completely fenced and air monitoring stations were installed around the perimeter to allow for continuous monitoring of particulates and emissions. To protect residence and utilities the team performed vibration monitoring. Over 2,600 truckloads of contaminated material was taken off-site and to limit impacts to residents, trips were coordinated to not coincide with school bus schedules.

Back to all
  • Liberty Hill project overhead
  • Liberty Hill project odor control
  • Liberty Hill project odor control
  • Liberty Hill project
  • Liberty Hill project odor control

Project Highlights

  • Excavated 93,000+ cy of MGP coal tar impacted materials
  • Transported, treated, and backfilled 40,000+ cy of soil
  • Demolished existing structures and remnant foundations
  • Installed excavation support systems including drilled piles, timber lagging, wales, & tiebacks
  • Performed dewatering & water treatment

Like what you see? Let's work together.

Work With Us