Project

Gloucester High School Flood Protection Project

Coastal Flood Protection

  • City of Gloucester
  • State & Local
  • Gloucester, Massachusetts

Project Overview

Charter built new flood protection along the Annisquam River to protect Gloucester High School, its athletic fields and adjacent parking from tidal flooding, storm surge and moon tides.

The centerpiece is a 1,441-linear-foot sheet pile floodwall along the riverbank, tied into earthen levees at each end and protected by scour protection on its landward side.

Charter’s Role

  • Installation of the sheet pile floodwall and riverbank scour protection
  • Construction of northwest and southeast earthen levees
  • Design adaptations, including shorter sheets and modified king piles, where existing utilities crossed the wall alignment
  • A crane-mat work platform to support installation equipment on soft soils
  • Pavement replacement, tree removal and replanting, erosion repairs and relocation of fences, benches and other site features

Outcomes & Benefits

The completed floodwall and levees give a busy school campus lasting protection against rising tides and coastal storms, delivered while working around existing utilities and challenging soil conditions.

Back to all
  • Sheet pile floodwall at Gloucester High School along the Annisquam River, Gloucester, Massachusetts
  • Sheet pile floodwall at Gloucester High School along the Annisquam River, Gloucester, Massachusetts
  • Sheet pile floodwall at Gloucester High School along the Annisquam River, Gloucester, Massachusetts
  • Sheet pile floodwall at Gloucester High School along the Annisquam River, Gloucester, Massachusetts
  • Sheet pile floodwall at Gloucester High School along the Annisquam River, Gloucester, Massachusetts

Project Highlights

  • 1,441 LF sheet pile floodwall along the Annisquam River
  • Earthen levees at both ends of the wall using approximately 870 CY of fill
  • Protects the high school, athletic fields and parking from storm surge and tidal flooding
  • Floodwall design adapted around deep, directionally drilled utilities
  • Constructed in about six months, January to June 2023